Sprint forecast

The forecast tells you when the sprint is likely to land and which tasks are at risk, with a reason for each. Open a sprint and pick Forecast in the Sprint insights panel under the chart.

What you see

  • Status: on track, at risk, late, not started or done.
  • Forecast finish: the sprint day the work is expected to finish, against the planned finish and the sprint's length.
  • Pace: how much work has been done compared with what the plan says should be done by now. 100% means exactly on plan.
  • Scope added: days of work added since the first snapshot.
  • ETA: the forecast as a calendar date, counted forward from today in working days.
  • By person: each lane's pace and forecast finish. The sprint lands when its slowest lane does.
  • At risk: tasks that are likely to miss, each with its reasons.

Press Why? for a one-sentence explanation of the main cause. Without an AI key it is built from the biggest risk; with one, OpenAI writes it from the same data.

How it is worked out

The forecast uses the live chart plus the sprint's daily snapshots. Nothing is sampled or guessed.

  1. Earned work. Each task earns part of its estimate based on its state: completed 100%, sign-off 90%, with QA 80%, in progress 40%, at risk 30%, blocked 20%, not started 0%. A 2-day task with QA has earned 1.6 days.
  2. Planned work by now. Tasks sit end to end on each lane, so the chart says how much of each lane should be done by the current day.
  3. Pace. Earned work divided by planned work, per lane. Pace is kept between 40% and 160% so one odd day doesn't swing the forecast wildly. A lane with less than half a day planned so far keeps a pace of 100%.
  4. Forecast finish. Remaining work divided by pace, added to today, plus any leave or distraction still ahead on the lane.
  5. The sprint lands on the latest lane's finish. It is late when that is more than a quarter of a day past the end, at risk when it is within half a day of the end or any task has a high-severity risk, and on track otherwise.

At-risk reasons

Reason When it shows Severity
Past the end Projected to finish after the sprint's last day High
Behind plan Should have been done by now but isn't near done High from a day behind
Blocked The task is blocked High
Marked at risk Someone set the task to At Risk Medium
Estimate grew The estimate rose by half a day or more since it first appeared Medium
Slipped Its planned end moved later by a day or more Medium
Came back from QA It went to QA and back to in progress High if more than once
Was blocked It spent two or more days blocked Medium
Stale pull request A linked open PR has had no activity for STALE_PR_DAYS days (3 by default) Medium

The history checks match tasks across snapshots by an origin id that each snapshot keeps, so renaming a task doesn't break them.

Why it works this way

  • It is explainable. Every number can be traced to the chart. When the forecast says a task is at risk, it says why, and the team can disagree with a specific reason instead of a black box.
  • It uses data you already have. Moving the day marker already takes a snapshot. The forecast just reads them.
  • It is deliberately simple. A pace per lane is easy to reason about and good enough to start a conversation. It is not a Monte Carlo simulation, and it doesn't pretend to be.
  • The ETA counts from today, not from the chart's day marker, so it stays honest if nobody has moved the marker for a couple of days.