Sprint forecast
The forecast tells you when the sprint is likely to land and which tasks are at risk, with a reason for each. Open a sprint and pick Forecast in the Sprint insights panel under the chart.
What you see
- Status: on track, at risk, late, not started or done.
- Forecast finish: the sprint day the work is expected to finish, against the planned finish and the sprint's length.
- Pace: how much work has been done compared with what the plan says should be done by now. 100% means exactly on plan.
- Scope added: days of work added since the first snapshot.
- ETA: the forecast as a calendar date, counted forward from today in working days.
- By person: each lane's pace and forecast finish. The sprint lands when its slowest lane does.
- At risk: tasks that are likely to miss, each with its reasons.
Press Why? for a one-sentence explanation of the main cause. Without an AI key it is built from the biggest risk; with one, OpenAI writes it from the same data.
How it is worked out
The forecast uses the live chart plus the sprint's daily snapshots. Nothing is sampled or guessed.
- Earned work. Each task earns part of its estimate based on its state: completed 100%, sign-off 90%, with QA 80%, in progress 40%, at risk 30%, blocked 20%, not started 0%. A 2-day task with QA has earned 1.6 days.
- Planned work by now. Tasks sit end to end on each lane, so the chart says how much of each lane should be done by the current day.
- Pace. Earned work divided by planned work, per lane. Pace is kept between 40% and 160% so one odd day doesn't swing the forecast wildly. A lane with less than half a day planned so far keeps a pace of 100%.
- Forecast finish. Remaining work divided by pace, added to today, plus any leave or distraction still ahead on the lane.
- The sprint lands on the latest lane's finish. It is late when that is more than a quarter of a day past the end, at risk when it is within half a day of the end or any task has a high-severity risk, and on track otherwise.
At-risk reasons
| Reason | When it shows | Severity |
|---|---|---|
| Past the end | Projected to finish after the sprint's last day | High |
| Behind plan | Should have been done by now but isn't near done | High from a day behind |
| Blocked | The task is blocked | High |
| Marked at risk | Someone set the task to At Risk | Medium |
| Estimate grew | The estimate rose by half a day or more since it first appeared | Medium |
| Slipped | Its planned end moved later by a day or more | Medium |
| Came back from QA | It went to QA and back to in progress | High if more than once |
| Was blocked | It spent two or more days blocked | Medium |
| Stale pull request | A linked open PR has had no activity for STALE_PR_DAYS days (3 by default) |
Medium |
The history checks match tasks across snapshots by an origin id that each snapshot keeps, so renaming a task doesn't break them.
Why it works this way
- It is explainable. Every number can be traced to the chart. When the forecast says a task is at risk, it says why, and the team can disagree with a specific reason instead of a black box.
- It uses data you already have. Moving the day marker already takes a snapshot. The forecast just reads them.
- It is deliberately simple. A pace per lane is easy to reason about and good enough to start a conversation. It is not a Monte Carlo simulation, and it doesn't pretend to be.
- The ETA counts from today, not from the chart's day marker, so it stays honest if nobody has moved the marker for a couple of days.
Also available
- In the customer portal as an ETA with a confidence level.
- On shared links, read-only.
- Through MCP as
get_forecastandlist_at_risk_tasks. - As the forecast landing date in the iCal feed.